Wm. Winkler Co. / Projects / Civil / MICCH Fort Hood

MICCH Fort Hood

MICCH Fort Hood

This project involved correcting drainage failures in areas A, C, & E. The scope of work included extending  concrete drainage channels to tie into earthen channels; elevating drainage channels for positive drainage; coordinating utility (water, power, fiber, communication, sewer, gas lines, etc.) relocation including relocating power and light poles; implementing erosion control measures; constructing sidewalks; constructing concrete wingwalls for skew box culverts; placing 765,079 SF (17.56 acres) of sod and temporary irrigation system; excavating trenches; and paving, grading, and subgrade.